Tuesday, June 28, 2011

We outta here! ....almost.

Our home is move-in ready (by the skin of our contractor's teeth, I do believe), but as Indy said, we may be done but we're not done. After we move, we will make a list of all that needs to be 'fixed.' Everything will get remedied; then, I believe (ehh...hope) that we will close on our mortgage, and this endless stream of bills with be no more.



As you know, we have installed a geothermal system in our house and insulated the entire house in foam. We have a very tight house. There benefits and downfalls to this. Benefit: less air leak from the interior to the exterior (thus lower energy costs). Downfall: less air leak from the interior to the exterior (ironic, I know). You see a house has to 'breathe,' and I talked about this earlier on in my great blogging adventure. In order to avoid 'sick house syndrome,' and, yes, there is such a creature. We have had Stroop's install an ERV system, or an energy recovery ventilation system, to help avoid this problem. This ERV system will let the house 'breathe' by exchanging stale internal air for fresh external air a set percentage of a 24-hour period. Currently, our ERV is set at 30%. Translated, this means that the ERV will exchange air for 30% of the time during a 24-hour period (a little less than 8 hours a day). The ERV technician was at our house the other day installing the system under the house, and he drew a diagram of house the contraption worked and took me under the house to show me how to change the setting (or percentage of exchange if necessary). Oh, that sweet smell of fresh air. Ahhh.


Quite a bit of work was done yesterday at the house, because as of Sunday evening (two days ago, mind you), there was no running water in the house. Let there be water! And, golly gee, we got water yesterday. And our refrigerator is hooked up. We also got to welcome back our washer and dryer that my brubby has so kindly kept operational for us. Shelving was installed (wood in the pantry and wire everywhere else). The front porch steps are supposedly complete as well. I would imagine the yard is still a muddy mess because of the current monsoon season, but eventually, Indy is going to pick up the rocks that litter the yard (with some machine he's rented) and bring in topsoil. Hopefully, they have removed the clutter in the garage or at least sorted through it. The leftover electrical supplies have been returned to the Southern Electric for credit. (Note: Always, always make sure that any extras get returned for credit. These credits certainly add up! We returned unused tile and grout to Lowe's a couple of days ago and that yielded a significant return in our wallets.) Once Builders Supply picks up the remaining lumber and other products, our house/garage/yard will start looking less like a construction zone and more like a home (surrounded by a sea of dirt or mud, of course).


Today, we hope Indy's cohorts can get our driveway in working order. They are to install two more culverts, smooth it out, and lay more gravel. The rain/muddy condition is the limiting factor.


 Tonight, we are moving clothes and Soxy down to Lynchburg. Soxy will actually be spending a few days at his grandmommy and granddaddy's house because there may still be workers going in and out of the our house. Poor Soxy's stress level would be off the charts. 


As I type this entry, I am surrounded by boxes and stuff that still needs to be thrown into boxes. We have cleaned bathrooms, emptied cabinets, vacuumed floors, changed addresses, called utility companies, and have eaten out or had sandwiches for the past two weeks. This will be the fourteenth time I have moved since moving out of my parent's house after high school. (I'm certain Noel's number rivals mine.) Moving is certainly a familiar nuisance, but a necessary one nonetheless. Last night, we were saying how we can't believe we have reached this point. This journey didn't start with purchasing land, nor saving up money, nor getting married. This journey started much, much sooner than that. In the words of Ty Pennington...Welcome Home White Family, Welcome Home!


We will keep you updated on the post-move progress (once we regain Internet access...I am turning the cable box in right after I complete this entry) because Hannah and Noel's great adventure isn't over until the mortgage broker sings. I also want to thank, in advance, the 'movers' who are volunteering their time and muskels to help us: Larry, Matt, Mom, Daddy, Jamie, Eli, Riley, Rosa Lee, Marianne, and Emma. We appreciate it!


Parting shot: Happy Anniversary to my bestest friend in the whole, wide world. (You are such a lucky dude!)

Wednesday, June 22, 2011

T minus 7 days and counting

We are one week until move day, people! And, I must say that my semi-vocalized frustration had quite the impact on our contractor, apparently. (I say semi-vocalized because I didn't have to vocalize much before he realized that I wanted him to get on the ball and get this house move-in ready.) After our phone conversation last Thursday, Noel and I drove up to the homestead that day and, there were ten (yes, ten!) cars parked up there 'getting shit done!' You couldn't wipe a smile off my face with and eraser. The framers were back and had finished our screened-in porch (minus the screen). The flooring dudes had finished tiling our shower and were in the process of grouting tile. Jose and his compadres were completing our interior bamboo steps, and while we were there, the stone masons appeared and got to work on our front porch steps.


Oh, now we can sit out on the porch and sip our mimosas!


So Soxy won't fall.

These gorgeous steps are really made from a grass. I really hope I don't run into a panda bear one day munching on our stairsteps. Pretty awesome!

The improv HGTV crew -- post mailbox installation.

Since last Thursday (aka the GSD day), the balusters have been put into place and the handrails stained on the staircase and overlook. The final round of painting was completed today. Carpet has been installed in our master bedroom. The hot water heater has been placed under the house. The plumber has been hard at work installing fixtures in our bathtubs and shower. A few of the contractor's men (if I knew your names I would thank you, but I do not) routed the gutter downspouts into the ground with corrugated plastic pipes to irrigate the yard while directing water away from the house. They also backfilled much of the area around the garage with dirt from one of the massive dirt piles that was created when the footers were dug. The electrician has installed the under-cabinet lighting, raised the pendant lights, and installed dimmer switches. Today, he was in the process of installing our speakers, TV mounts, and rope lighting. This is his last day on the job at our house, and we truly appreciate the work he has done. (Thank you, Jon!) The dishwasher would have been installed today if the cabinet people (ahh, the headache reappears) had actually made the slot large enough for a standard size dishwasher, but they did not (surprise, surprise). Alas, they must return to correct their mistake, but their return did not occur today (and we were ensured by them that it would).


Gutter engineering.

After the mounting frustration on Thursday, I typed out lists for the electrician, Indy, and the plumber (although the plumber's list was extremely short). We wanted them to know what we noticed needed to be done. Apparently, they expect lists...like lists. If only I had know that this was kosher earlier in the process, I would have been like Santa...lists for everyone! We, of course, kept a copy of each person's list so we can walk through and around the house and check off what has been completed. Lists give the A-type personality something tangible. Makes me feel a bit more in control of the situation. Not to mention, we always forget to mention things to Indy. To make a list, we analyzed each room as to not miss anything.


Today, Noel met with the closet shelving elf (get it...the shelf elf...ha!) to tell him how we wanted each closet set up. The cleaning ladies are coming tomorrow to rid our house of dust and trash. The area around the house still needs some tending. The burn pile in the back needs to be scooped up and hauled off. The yard needs to be free of rocks and adorned with a fresh coat of topsoil. Backfilling needs to occur around the house. And, we need a screen for that screened-in porch. The driveway, good grief, the driveway needs a couple of culverts installed, needs to be graded, and desperately needs crushed gravel. Of course, as this has kicked into high gear, monsoon season has fallen on Lynchburg. I didn't think I would say this (in a time when we so desperately needed rain), but rain, rain go away come back again when we've moved in and need a lazy, rainy day.


The interior of the house is so much closer to completion than the exterior, but we just need this thing to be livable in seven days. We might just make it. Come on Indy!


Parting shot: The muffin (our wonderful wiggling muffin)

Thursday, June 16, 2011

On the twelfth day before moving in my contractor gave to us...no progress!

As I type this blog, Queen's "Under Pressure" is blaring in the background in an attempt to calm down a very frustrating evening and morning. If I was an inanimate object, I would resemble a food canner with that jiggling thing on the top vibrating like mad to let off steam. I know I have used this line before in the blog but I am funneling Frank Costanza yet again..."Serenity now!!"


Here is the timeline people. We have twelve days to get this house done. We are moving from this townhouse in thirteen days, June 29th, mind you. Less than two weeks. What is left? Oh, the porch steps, interior steps, interior balusters and handrail, screened-in porch, staining the concrete, finishing the electrical work, finishing the plumbing work (but, wait, our plumber can't finish his job until the tile boys finish our shower), grouting the tile, cutting an air vent for the dryer, returning and crediting unused supplies, installing carpet, installing an interior door in the garage, caulking around the exterior doors, sanding and restaining the exterior doors, installing doorknobs, patching the hole in the kitchen ceiling, installing our rope lighting and dimmer switches, painting the hallway, giving our closets shelving, installing the hot water heater, refrigerator, and dishwasher, trenching for the plumbing to our garage (then covering it up), filling in around the house site with the dirt they removed to do footers, bringing in topsoil so we can have grass, dumping some more gravel on our driveway, hauling off the junk they have used to junk-up the house site, and cleaning our house of all the dusty remnants. That is all. Twelve days, that's all I'm saying. We are installing our mailbox today, at least we know that will get done. Dad has offered numerous times to finish it for us. Why, oh, why didn't we let him?!


Apparently, this situation is not unique to us. I have heard from numerous people who have built a house (through a contractor) that once the house reaches the point where it looks like it's almost complete all of the workers disappear.


On another note, our plumber has done everything he can do until this point. He has installed our toilets (which we thought were going to be low-flow but that is another story for another day) and faucets. We did have to exchange the faucets we bought for the upstairs bathroom because the extensions on the bottom were not long enough to reach through the granite. This worked out to our benefit because the faucets we exchanged them for were a bit cheaper. 


In the mean time, we have been moving boxes from Murfreesboro to Lynchburg as we can. With each trip we bring another load as we will do today. Our goal is to have only large furniture remaining by the 29th. 


Note this 'installment' (as my poppa calls it) is just a dose of reality. As I mentioned when beginning this blogging adventure, we were going to be brutally honest about our experience. One day we'll look back and laugh...maybe. Ha! Ha!

Tuesday, June 7, 2011

And, we're rounding third...

Over the past few weeks, finishing touches have made their way into our new homestead. Whoop! Whoop! The flooring boys have completed the tile in utility room, upstairs bathroom, and the floor of the master bathroom. Working on the tile in the master bath shower will take a bit longer. The tile in these rooms has not been grouted because the flooring ringleader (Adam) said that the grout will just get dirty if they do it now. He said grouting is typically completed toward the end of the process. Adam and his cohorts have also completed our hardwood flooring, and the bamboo is gorgeous. This bamboo, though, caused it's share of bumps in the road. We purchased strand-woven bamboo (tremendously stronger than oak) from SimpleFloors in Georgia. When Adam attempted to nail down the bamboo with a nail gun, the nails would fold because the wood was entirely too strong to penetrate. After much help from our sales rep at SimpleFloors, Indy and Adam decided that gluing the floor was a much better option. We want to commend Indy, Adam, and our wonderful sales rep Lyza for their patience and diligence in remedying this problem. You guys rock!


Meet the floor dudes.

Floor dude vs. bamboo and glue

Trees are thanking us right about now. You are welcome!

We ordered carpet yesterday, and the style for the bonus room is on backorder until June 24th. Nevertheless, the bedroom carpets should not be a problem and should be delivered next week.


And, finally, we have granite! The granite was installed last week once the flooring got installed under the kitchen island. Luckily, the granite looks great. (Considering we couldn't remember what in the world we had picked out. Ha!) 

Can't you just see Noel cooking away?!

And, I can totally see him cleaning up all the dishes after the delicious dinner he fixed me.


A few weeks ago Keith and his crew rejoined the workforce at our homestead to give us a deck on the back of the house and a lean-to on the back of the garage. They threw both up in a day's time. Pretty efficient really. We told them to hold off on the railings for the deck, because we wanted to install the taught wire (you know, for a modern look). So we started doing research on taught wire railing systems. We got a quote, and the quote is so laughable I just can't bear to put it in this blog. Needless to say, the taught wire wasn't just over our budget, it was waaaaaay out of our price range. We still needed railing, though, and my dad decided he would be the one to supply us with some nice wooden railings, which now looks great by the way. (Thanks, Daddy! And I'm sorry I don't have a pic to display your fine craftsmanship, but Indy was impressed.) He will be the first to tell you that he is the most efficient subcontractor we've had in this process, and for argument's sake, we'll agree.


The ceilings of our porches have been stained and installed.


The stained ceiling of our front porch.


John (our electrician) had been busy at work all last week finishing up the electrical in the house. I believe we are still at the electric company's mercy to come pull the electric line to the house from the transformer, but they move as slow as molasses down there. We are also still attempting to get credit from the electric company for going 'green' with our geothermal system, insulation, and windows. The guy who evaluates this for us said he would come once the appliances have been installed. 


The soffit/gutter guys have started doing their job, but soon after starting they disappeared and have been MIA for well over a week now. Hello, boys! We need gutters if you want money. I see only one way to remedy this situation.


Stroops (our geothermal company) installed our thermostats and turned on the units, and we are not certain that either unit is functioning appropriately. Wonderful! Indy has made them aware of the problem as have I, so, hopefully, we'll get some arctic air blasting through that house soon.


We are moving from this townhouse to the homestead on June 29th come hell or high water. And, please consider this a solicitation for volunteers. If you don't volunteer, we will hunt you down and make you miserable. :) Some boxes and pieces of furniture have already made their way down to Lynchvegas and are sitting in the upstairs of our garage. We are nearing the end of the long adventure, and we are very ready to jump to the next. (Yeah, we get bored quickly if you didn't know.) However, we seem to think that this next endeavor will keep us on our toes a bit more than a house. 


Parting shot: A HUGE congrats to my bro and his new wifey! (Nayer, you can't bring him back. May the force be with you.)